Knowledge Areas | Major Processes | Primary Inputs | Tools & Techniques | Primary Outputs |
| | | | |
PROCUREMENT | PPSSAC | | | |
Plan Purchases & Acquisitions | Determining what to procure and when and how (make or buy) | 1. 2. Organizational Process Assets 3. Project scope statement 4. WBS 5. WBS Dictionary 6. Project Management Plan | 1. Make or buy analysis 2. Expert judgment 3. Contract types | 1. Procurement mgmt plan 3. Make or Buy Decisions 4. Requested Changes |
Plan Contracting | Preparing the documents needed to do contracting. Document requirement and identify sellers | 1. Procurement management plan 2. Contract Statement(s) of work 3. Make or Buy Decisions 4. Project Management Plan | 1. Standard forms 2. Expert judgment | 1. Procurement documents 3. Contract Statement of work (updates) |
Request Seller Responses | Obtaining quotations, bids, offers, or proposals (answer questions) | 1. Organizational Process Assets 2. Procurement Management Plan 3. Procurement Documents | 1. Bidder conferences 2. Advertising 3. Develop qualified sellers list | 1. Qualified sellers list 2. Procurement Document Package 3. Proposals |
Select Sellers | Involves the receipt of bids or proposals and the application of evaluation criteria to select a seller. Also involves applying evaluation criteria. | 1. Organizational Process Assets 2. Procurement Management Plan 3. Evaluation Criteria 4. Procurement Document Package 5. Proposals 6. Qualified Sellers List 7. Project Management Plan | 1. Weighting system 2. Independent estimates 3. Screening system 4. Contract Negotiation 5. Seller Rating System 6. Expert Judgment 7. Proposal Evaluation Techniques | 1. Selected Sellers 2. Contract 3. Contract Management Plan 4. Resource Availability 5. Procurement Management Plan (Updates) 6. Requested changes |
Contract Administration | Ensuring that the seller’s performance meets contractual requirements | 1. Contract 2. Contract Management Plan 3. Selected Sellers 4. Performance Reports 5. Approved change requests 6. Work Performance information | 1. Contract change control system 2. Buyer conducted performance review 3. Inspections and audits 4. Performance reporting 5.Payment system 6. Claims administration 7. Records management system 8. Information technology | 1. Contract Documentation 2. Requested Changes 3. Recommended Corrective actions 4. Organizational Process assets (Updates) 5. Project Management plan (updates) * Procurement Management Plan * Contract management plan |
Contract Closeout | Product verification and administration closeout (finish) | 1. Procurement management Plan 2. Contract management plan 3. Contract documentation 4. Contract closure procedure | 1. Procurement audits 2. Records Management System | 1. Closed Contracts 2. Organizational process assets (Updates) |
Procurement Processes Repetition - When the project obtains products and services (project scope) from outside the performing organization, the processes from procurement planning through contract closeout would be performed once for each product or service item.
Contract – Subjects covered include Responsibilities, authorities, law and terms, technical and management approaches, financing, schedule, payments and price. Contract negotiations conclude with a document that can be signed by both buyer and seller, that is contract. The final contract can be a revised offer by the seller or counter offer by the buyer.
PLAN PROCUREMENT (OP)
Procurement Management Plan – Describes how procurement will be managed till contract closure. It includes Type Of contract, who prepares independent estimates, standardized procurement documents, Constraints and assumptions, identifying seller list etc.
Contract SOW – Developed from Scope Statement, WBS and WBS Dictionary describes procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing it.
Type of Contract SOW:
- Performance: what final product should be able to accomplish, car with a speed of 240 KM per hr (T&M, CR; IT, R&D)
- functional: end purpose or result, car with 6 seats (T&M, IT, R&D)
- design: what work is to be done, built car as per the design (T&M, FP, construction)
Make or buy decisions: Costs - Direct costs are costs incurred for the exclusive benefit of the project (e.g., salaries of full-time project staff). Indirect costs, also called overhead costs, are costs allocated to the project by the performing organization as a cost of doing business (e.g., salaries of corporate executives).
PLAN CONTRACTING (OP)
Procurement Documents – Common names for different types of procurement documents include: Invitation for Bid (IFB), Request for Proposal (RFP), Request for Quotation (RFQ), tender notice, Invitation for Negotiation, and Contractor Initial Response. Procurement documents are rigorous enough to ensure consistent, comparable responses but flexible enough to allow seller suggestions for better ways to satisfy the requirements. Seller is allowed to propose alternative solution in a separate proposal.
It has 1. Information for sellers 2. Contract SOW 3. Proposed terms and conditions of the contract (Legal & Business)
Evaluation Criteria
Proposal - technical approach, Bid, Tender and quotation – price
REQUEST SELLER RESPONSE
Bidder Conferences (TT) – Also called, as Contactor Conferences, Vendor Conferences and Pre-Bid Conferences are meetings with prospective sellers prior to preparation of bid or proposal, ensures clear and common understanding of procurement needs.
Procurement Document Package (OP) – Buyer prepared formal request sent to each seller and is the basis upon which a seller prepares a bid for the requested products, service or result.
Procurement Documents
- Request For Proposal/Tender (RFP, RFT ) – Requests for Price and Detailed Proposal (CR)
- Invitation for Bid/Request for Bid (IFB, RFB) – One Price (FP)
- Request for Quotation – Price Quote per item (T&M)
Select Sellers – Tools & Techniques
- Weighting System – Numeric Weight to each criteria, rating sellers, selection based on total weight
- Independent Estimates – called “Should-Cost”, prepared by procuring organization.
- Screening System – Establish minimum performance requirement for one or more criteria and use 1 & 2 methods
- Contract Negotiation – Project Manager may not be the lead negotiator, PM team may be present during negotiations for providing any clarification of project’s technical and management requirements.
- Seller Rating Systems
- Expert Judgment
- Proposal Evaluations techniques – Use some Expert judgment and evaluation criteria to rate and score proposals.
Output
Contract Management Plan – Lists documentation, delivery and performance requirements that the buyer and seller must meet. The plan covers the contract administration activities throughout the life of the contract. Part of PMP.
Selected Seller
Contract
Resource Availability
Contract Administration – Ensures the seller meets the performance requirements of the contract. Because of legal considerations many organizations treat contract administration as a separate administrative function from the project organization. Contract administration includes application of the appropriate project management processes to the contractual relationships(s) and integration of the outputs from these processes into overall management of the project.
Contract administration also has a financial management component. Payment terms should be defined within the contract and must involve a specific linkage between seller progress made and seller compensation paid.
TT:
Contract CC system
Buyer conducted perf review
Inspection and audits
Performance reporting
Payment System – Usually handled by accounts payable system of the buyer. It includes reviews & approvals by PM team.
Claims Administration – Contested Charges (claims, Disputes or appeals) are those where buyer and seller cannot agree. If both parties do not resolve a claim it is handled according to the resolution procedures established in the contract. Contract clauses can involve arbitration or litigation and can be invoked prior or after contract closure.
Records Management System – Set of procedures and automation tools that are consolidated as part of PMIS to manage contract documentation and records.
IT
OP:
Organization Process Assets (After Contract Administration) –
1. Correspondence – In addition to documentation, it is a record of all the written and oral communication.
2. Payment Schedules and Requests
3. Seller Performance evaluation documentation
PMP updates – Procurement Management Plan and Contract Management Plan.
Contract Closure
Procurement Audit – Review of procurement processes from Plan purchases to Contract administration. Aims to identify successes and failures.
Records Management System
Contract closeout is similar to administrative closure in that it involves both product verification (Was all work completed correctly and satisfactorily?)
Administrative closeout (updating of records to reflect final results and archiving of such information for future use).
Administrative Closure (Internal)—generating, gathering, and disseminating information, to formalize a phase or project completion.
Contract Closeout—completion and settlement of the contract, including resolution of any open items. (External )
Difference between Contract Closeout and Admin Closure
1. Contract Closure comes first 2. AC is done at end of each phase or project, CC is done only once at the end of Contract 3.AC – Lessons learned CC – Procurement audit 4. AC – Less Formal CC – More Formal.
a contract, an agreement, a subcontract, a purchase order, or a memorandum of understanding.
Buyer(Give Order )----
Seller ----Invoice------à Buyer (Pay order)
Contract Types and Risk | 1. Fixed Price 2. Cost-Reimbursable 3.Time & Material |
CR | Buyer has risk, as total cost are unknownYou are buying “what to do” from seller. |
Cost plus fee or Cost Plus Percentage of Cost (CPPC) | No valid for federal contracts. Sellers are not motivated to control cost, used when buyer can tell what is needed then what to do. Seller write SOW. Bad for buyer |
Cost Plus Fixed Fee (CPFF) | Used for research and development contracts (which generally have low level of detail in the scope); fixed fee can change if there is a change to the contract (usually through change orders). The risk rests with the buyer. This is the most common cost reimbursable contract. |
Cost Plus Incentive Fee CPIF) | Buyer and seller share in savings based on predetermined %s; long performance periods and substantial development and test requirements (incentive to the seller to perform on or ahead of time) Cost plus agreed fee plus a bonus for beating the objective |
Cost plus Award fee | Similar to CPIF but award amount is amount is determined in advance and apportioned out depending on performance. |
| · In Cost plus contract, the only firm figure is the fee |
T & M | Used for small amount contract. Good if the buyer wants to be in full control and/or the scope is unclear/not detailed or work has to start quickly. Profit factor into the hourly rate. Fixed rate but variable total cost. They are open ended. |
Fixed price or Firm Fixed Price (FFP) | Buyer defines reasonably detailed specifications (e.g. SOW). Shift risk to seller. Good when deliverable is not a core competency. Fixed Price (FP) is the most common type of contract in the world. Seller is at risk. |
Fixed Price Plus Incentive Fee (FPIF) | Incentives for fixed price contract. The inventive is same as CPIF. High-value projects involving long performance periods |
Fixed Price Award Fee | “bonus” to the seller based on performance (e.g. 100K + 10K for every designated incremental quality level reached. Award fee is decided in advance. |
Fixed Price Economic Price Adjustment (FPEPA) | Allow Price increase if the contract is for multiple years |
Purchase Order | A form of contract that is normally unilateral and used for simple commodity purchases. It is simplest type of fixed price contract and is usually unilateral(Signed by one party instead of bilateral) |
Contract type Vs Risk | FP – FPIF – FPAF – FPEPA – T&M – CPIF – CPAF – CPFF - CPPC Fixed Price – T&M - Cost Reimbursable Buyer’s risk from low to high Seller’s risk from high to low |
Cost Reimbursable
Advantages | Disadvantages |
Simpler contract SOW | Required auditing sellers invoices |
Usually required less work to write the scope than FP | Requires more work for buyer to manage |
Generally lower cost than PL because the seller does not have to add as much for risk. | Seller has only a moderate incentive to control costs |
| Total price is unknown |
T&M
Advantages | Disadvantages |
Quick to create | Profit is in every hour billed |
Contract duration is brief | Seller has no inventive to control costs |
Good choice when you are hiring to augment your staff | Appropriate only for small projects |
| Requires the most day to day oversight from the buyer |
Fixed Price
Advantages | Disadvantages |
Less work for buyer to manage | Seller may under price the wok and try to make up profits on change orders |
Seller has a strong incentive to control cost | Seller may not complete some of the SOW if they begin to loose money |
Companies have experience with this type | More work for buyer to write the CSOW |
Buyer know the total price at the project start | Can be more expensive than CR is the CSOW is incomplete. The seller will add to the price for their increased risk. |
Elements of a Contract | |
Offer | Assent to certain terms by both parties |
Acceptance | Agreement, written or spoken |
Consideration | Something of value |
Legal Capacity | Able to contract |
Legal Purpose | No violation of public policy |
Stages of Contract Negotiation | |
Protocol | Introductions |
Probing | Identify concerns, strengths, weaknesses |
Scratch bargaining | Actual bargaining |
Closure | Positions summed up |
Agreement | Documenting |
Specification - precise description of a physical item, procedure, or service. The SOW supplements the specification in describing what must be done to complete the project.
Privity - legal relationship that exists between any contracting parties (e.g. if company “A” hires “B” and “B” subcontract to “C”, “C” is not legally bound by anything “A” can say; the privity is with “B”)
Waiver - a party can relinquish rights that it otherwise has under the contract. Forebearance can mature into waiver.
Force Majeure – Act of God, Floods, Fire etc
Indemnification – Liability, who is liable
Retainage – withholding of funds under contract. Amount of money usually 5% to 10% withheld form each payment. This money is paid when work is complete.
Warranty - assurance of the level of quality to be provided
A contract ends by: | |
Successful performance | |
Mutual agreement | Last two are Termination |
Breach of contract | |
Terms and Conditions – the project manager must uphold the Terms and Conditions of the contract, even if it meets the needs of the project, it has to also meet the requirement of the contract.
Liquidated damages -
Contract Control System vs. Project Control System – they both include procedures. The contract control system requires more documentation and more signoff.
Work Authorization Systems – can be used to coordinate/control what time and sequence work is done. It helps with integrating tasks into a whole.
Performance Scope of Work – describes the performance – not the functionality-- required by the customer
Independent Estimate – most concern with costs, comparing cost estimates with in-house estimates or with outside assistance (part of Source Selection)
Procurement Audit – structured review that flush out issues, and set-up lessons learned. Helps ensure problems are resolved for future projects. Identify successes and failures that warrant transfer to other procurements.
Beneficial Efficiency – when the work is being used for the intended purpose and has been certified
Terminating contract for Convenience – if a project is terminated before it is complete, the level of extent of completion should be established and documented.
Material Breach – Breach so large that it may not be possible to complete the work.
Sole Source (not Single Source) – Only one seller, it might be a company that owns a patent.
Contracting | |
Centralized | Decentralized |
+ More economical | + Project Manager has more control |
+ Easier to Control | + Contracting personnel are more familiar with project |
+ Higher degree of specialization (expertise) | + More flexible and adaptable to project needs |
+ Orders can be consolidated | - Duplication of contracting efforts |
- May become a bottleneck | - Higher costs |
- Less attention to special needs | - No standard policies |
Negotiating Tactics | |
Deadline | Strategic Delay |
Surprise | Reasoning Together |
Limited Authority | Withdrawal |
Missing Man | Unreasonable |
Fair and Reasonable | Suggesting Arbitration |
| Fait Accompli (A done deal) |
Notes: I am not the writter of this post, please thanks the anonymous writter
"Hi There,
ReplyDeleteVery Nice post on PMP Notes.That was very helpfull.keep posting"
Hi Elisabeth,
ReplyDeleteYou are right.These PMP Study Notes
Hi friend we providing the Pmp training in Hyderabad of various online training.
ReplyDeleteYour thinking toward the respective issue is awesome also the idea behind the blog is very interesting which would bring a new evolution in respective field. Keep update more information.
ReplyDeleteProcurement Management Software in India
Procurement Management Software
Procurement Management Software in Chennai
Great post! I am actually getting ready to across this information, It's very helpful for this blog.Also great with all of the valuable information you have Keep up the good work you are doing well.
ReplyDeleteProcurement Management Software
Purchase Management Software
e Procurement Management Software
A nice article here with some useful tips for those who are not used-to comment that frequently. Thanks for this helpful information I agree with all points you have given to us.
ReplyDeleteProcurement Management Software
Purchase Management Software
e Procurement Management Software
Procurement Management System